|
The Mackie Process - Revolutionary
Development of the Crack Free Rail
By Sydney S. Slaven
Irwin Cameron, {I.C.}, Mackie was a metallurgist employed by the
Dominion Steel & Coal Company who solved the problem that had
plagued railway travel since its beginning – that of rails
cracking, often with disastrous results, under the stress of weight.
C. Mackie was a graduate of Dalhousie University who began work
with Dosco in 1902 at the Sydney works. He retired 62 years later
as the Dosco Director of Metallurgy.
Since the middle of the 19th century, {when steel replaced wooden
rails}, railways were tormented by rails that cracked under the
pounding of a train’s wheels. These were rails that at the
time seemed flawless but, as locomotives carried increasingly larger
loads, the problem became more pronounced. Of course this led to
sudden, without warning, devastating derailments.
In 1918 laboratory studies discovered the existence of minute cracks
deep inside newly manufactured rails. These cracks were hydrogen
bubbles which came to be known as “shatter cracks, thermal
ruptures and fissures.” Over time the weight of usage caused
the rails to snap without warning. However, no cure for the problem
was forthcoming at the time although it was agreed that the problem
of “shatter cracks” was introduced at some stage of
manufacturing.
Metallurgical scientists tested on the assumption that the problem
originated from the high temperatures required to roll rails. Tests
were conducted unsuccessfully for many years.
Mackie begin his own experiments in 1930 at the Sydney Mill. Because
of the lack of success of high temperature experiments he looked
in the opposite direction. He discovered that the cracks were occurring
in the steel at low temperatures. Therefore, he concluded that the
answer should lie in the slowing down or controlling of the cooling
process of the red-hot rails.
Extensive testing verified Mackie’s theory and by July, 1931,
Sydney Steel was producing the world’s first crack or “shatter”
free rails.
Method of Controlled Cooling
{1} Rails allowed to cool naturally on the mill cooling beds until
below 900 degrees F.
{2} Before they reach the temp. of 660 degrees F. they are assembled
in groups of 4 or 5 rails with the heads turned up.
{3} Then they are lifted by a magnet crane and stowed in large sheet
iron boxes. These boxes are 42 feet in length, 5 foot 6 inches wide
and 8 feet 6 inches deep. Each box will hold 120 rails of 130 pound
per yard section. The different tiers are separated by skid bars.
{4} When a box is filled a cover is placed upon it and the rails
are allowed to cool slowly for from 24 to 30 hours, by which time
they will have reached a temperature within 100 degrees F. of the
surrounding atmosphere.
{5} They are then ready to be discharged and finishing operations
performed.
C. Mackie received a Canadian patent on his process and the Canadian
National Railroad was the first railway to exclusively use his rails.
By 1933, Canada’s other rail mill at Algoma was using his
method to produce rails for the Canadian Pacific Railroad. Within
a few years most of the world’s major countries were manufacturing
the safe rail produced by the Mackie Process.
When Mackie applied for a U. S. patent, Bethlehem Steel began legal
action to block the patent. It dragged through the courts for seven
years before Bethlehem relented and began paying Mackie royalties.
Perhaps Mackie received some consolation from the fact that every
rail manufactured in Canada using his process had Mackie stamped
on its side.
|